Posts by Sour934r35gncek348
CIV-001
Scope Of Work: Construction of New Boundary Retaining Walls and Bulk Earthworks to Platform
Duration: 4.5 Months
Project ...
IND-001
Scope Of Work: Retaining wall, warehouse foundations and new service block
Duration: 8 Months
Project Value: R2 260 000
...
RES-001
Scope Of Work: Construction of New Proposed 4-storey dwelling
Duration: 12 Months
Project Value: R4 Million
Client...
RES-002
Scope Of Work: Additions and Alternations to residential dwelling
Duration: 18 Months
Project Value: R5.8 Million
...